If you are moving, the biggest question is usually how long the power will take to come on. The average electricity connection time is not the same across Australia because each state and distributor works to different service windows.
This 2026 guide compares current electricity and gas connection benchmarks by state, using published distributor and regulator information.
Rather than giving one broad national estimate, it shows where connections can be faster, where extra steps may slow them down, and what movers should allow for before move-in day.
Market Overview: Key Insights 2026
- VIC: eligible Jemena electricity move-ins can be completed the same day when the retailer request reaches the network before 3pm.
- QLD: Energex publishes a 1pm service-order cut-off for eligible same-day reconnections. Later valid requests generally move to the next business day.
- ACT: Evoenergy uses a 2pm business-day deadline for eligible same-day retailer requests.
- Meter work can add days: Energex publishes 5 business days for a new connection, 10 business days for additions and alterations, and 20 business days for meter reconfiguration once requirements are met.
- Smart meters can speed up move-ins: many Victorian electricity jobs can be completed remotely rather than waiting for a routine site visit.
How Long Does an Electricity Connection Take on Average?
There is no single official national average. For established homes, published network benchmarks range from eligible same-day connections to one or two business days, while rural, safety and meter-work cases can take longer.
Electricity distributors generally publish service standards or connection windows rather than national median performance figures. That means the best planning benchmark is the rule used by the network serving the property.
| State / Network | Published Electricity Benchmark | Same-Day Window |
|---|---|---|
| VIC, established premises | Usually within 1 business day after the retailer requests connection | Jemena: eligible same-day request before 3pm |
| NSW, Ausgrid area | By the end of the next business day, or second business day after a late request | After-hours and weekend options may be offered separately |
| QLD, Energex area | Same day when a valid service order arrives by the applicable deadline, otherwise next business day | 1pm in most eligible locations |
| SA, SA Power Networks | Eligible same-day move-in can be requested through the retailer, subject to site conditions | Retailer contacted before 9pm |
| ACT, Evoenergy | Connection by the nominated required date | Eligible same-day retailer request by 2pm |
The practical average electricity connection time therefore needs network context. A ready-to-connect property with a suitable meter is very different from a site needing additional physical work.
The guide to how long electricity and gas take to connect explains how retailer cut-offs, meter type, access and non-standard work can change the timeframe.
Extra Meter Work Can Increase the Connection Time Significantly
Energex publishes different service targets depending on the type of electricity work required. A straightforward new connection has a shorter benchmark than additions, alterations or meter reconfiguration.
connection
alterations
reconfiguration
What this means for movers: do not use a same-day move-in benchmark for a property that needs additional meter or network work. The job type can change the published service target from a few days to several weeks.
Source: Energex guaranteed service levels. These figures apply to the specified work categories once relevant requirements are met and should not be confused with a standard existing-home move-in reconnection.

How Long Does a Gas Connection Take on Average?
There is no comparable national average for established-premises gas move-ins. Timing depends on the gas distributor, meter status, site access and whether the property already has a gas connection.
Gas needs to be interpreted separately from electricity because physical access and distributor scheduling can matter more often.
| State / Network Example | Published Gas Benchmark |
|---|---|
| VIC, existing meter move-in | No single statewide benchmark. Timing depends on the retailer service order, meter status and property access. |
| VIC, new gas service | Multinet and Australian Gas Networks publish a 20-business-day target once the site is ready, where a new gas connection is permitted. |
| NSW | No single statewide established-premises benchmark. Timing varies by distributor and address. |
| QLD / SA | No single statewide established-premises benchmark. Availability depends on the property and network. |
Electricity and gas should therefore be planned separately. Several electricity networks have published same-day pathways, while gas timing is more closely tied to meter condition, property access and the type of connection.
A brand-new gas service can have a multi-week published target. Moving into a property with an existing meter is a different job and should not automatically be given the same timeframe.
How Many Connections Are Completed the Same Day?
No national same-day completion percentage is published. What is available publicly are the cut-off rules that determine when eligible same-day electricity processing can occur.
Several major networks publish a same-day pathway. Jemena uses a 3pm receipt deadline for eligible move-ins, Energex publishes 1pm for eligible standard reconnections in most locations, and Evoenergy uses 2pm for eligible business-day requests.
Same-day availability does not mean every request submitted that morning will be completed that day. The retailer must first create the correct service order and send it to the network before the cut-off.
The meter and property also need to be suitable. Blocked meter access, a safety issue or additional work can push the connection beyond the published same-day pathway.
Smart meters are useful context because they can remove the need for a routine physical visit. The guide to smart meters vs analogue meters when moving explains why remote capability can help without guaranteeing same-day completion.
Which States Are Fastest and Slowest?
The published service rules are not directly comparable enough to fairly rank whole states from fastest to slowest. Distributor area, request time, meter type and job type can all change the result.
Victoria, Queensland, South Australia and the ACT all have published pathways that can support same-day electricity connections in eligible circumstances.
Victoria is a useful example. The Essential Services Commission says an established property is usually reconnected within one business day after the retailer requests connection, while Jemena also publishes a 3pm same-day cut-off in its network area.
Smart meters can make Victorian move-ins more flexible by removing the need for some physical site visits. They do not remove retailer processing or distributor deadlines.
Queensland shows why statewide rankings can be misleading. Energex has an eligible same-day pathway in many areas, while its published service standards for some other locations can be substantially longer.
Best comparison: check the distributor serving the exact address rather than choosing a state based on a single published timeframe. Different networks can operate inside the same state.
What Causes Connections to Take Longer?
The most common published delay factors are missing the distributor cut-off, blocked or unsafe meter access, additional meter work, safety requirements and longer network standards in some rural areas.
For movers asking how long connections take in Australia, these delay factors are often more useful than one national average.
Missing the cut-off. A late service order can move an otherwise simple connection to the next business day.
Blocked meter access. Gates, locked meter rooms or inaccessible main switches can stop a scheduled job.
Meter or network work. Reconfiguration, alterations or a new connection can turn a short move-in job into a multi-day process.
Safety requirements. A distributor may not complete the job until the site meets its connection requirements.
Location. Rural or non-standard network areas can have longer published service windows.
SA Power Networks, for example, warns that meter or main-switch access problems can prevent a move-in connection from being completed and may require a new retailer request.
After checking the likely delay factors, compare connection fees and timing in your state because urgent, after-hours and non-standard jobs can affect both timing and cost.
How Were These 2026 Benchmarks Checked?
The benchmarks on this page were checked against current distributor and regulator guidance in October 2026. They are published network service windows and targets, not Move-in Connect’s internal median connection data.
This distinction matters because a guaranteed service level, same-day cut-off and average customer experience are not the same measurement.
New-build connections, supply upgrades and meter alterations have also been kept separate from ordinary established-home move-ins so a long construction-related timeframe is not presented as a normal moving-house benchmark.
Distributor standards can change. This page should therefore be reviewed at least every six months and the visible last-updated date should be kept current.
Based in central Melbourne, our connections team helps movers check the requirements for their new address. You can read reviews of the Move-in Connect Melbourne team on Google Maps or call 1300 362 580.

How Should You Use These 2026 Benchmarks?
Use the published figures as planning benchmarks rather than guarantees for every address.
The strongest pattern is straightforward. Established electricity can be quick where the service order is submitted early, the meter is suitable and no extra work is required. Gas, new connections, meter changes and safety-related jobs need more time.
Book early enough that you do not have to depend on the final same-day cut-off. If the property needs meter work, network attendance or a new service, allow additional time before moving day.
Check the Connection Time for Your New Address
Connection times depend on the distributor, meter and type of work required. Check the address before relying on a statewide estimate.
Frequently Asked Questions
What Is the Average Time to Connect Electricity in Australia?
There is no single official national median. Several major networks publish same-day or next-business-day pathways for established premises, while rural, safety and non-standard jobs can take longer.
Which State Connects Electricity Fastest?
There is no fair statewide ranking from the published benchmarks because different distributors cover different network areas and job types. Compare the network serving the exact address instead.
Why Does Gas Take Longer Than Electricity?
Gas connections more often depend on physical meter access, field work and distributor scheduling. Electricity can sometimes be completed remotely where a suitable smart meter is installed.
Does This Include New-Build Homes?
No. New builds can require meter installation, network work and distributor scheduling, so their connection time can be substantially longer than a normal move-in at an established property.
How Often Is This Data Updated?
The benchmarks should be reviewed at least every six months. Distributor cut-offs, service standards and connection processes can change, so each official source should be checked again before updating the page.
Can Meter Work Make My Connection Take Longer?
Yes. Published Energex benchmarks show how the job type can materially change the timeframe, from 5 business days for a new connection to 20 business days for meter reconfiguration once the applicable requirements are met.
Sources and further reading
Where the facts in this energy guide come from.
- Jemena: Moving home or premisesCited in the text above.
- Energex: Guaranteed service levelsCited in the text above.
Was this guide useful?
Thanks for letting us know.