Utilities for a New Café or Restaurant: What to Book and When

Opening week is a bad time to discover the oven needs more power, the gas account was never opened or the EFTPOS terminals have no internet.

Utilities for a New Café or Restaurant: What to Book and When
On This Page
  1. What Utilities Does a Café or Restaurant Need Before Opening?
  2. What Should You Book First?
  3. Does a Commercial Kitchen Need Three-Phase Power?
  4. What Is Different About a Commercial Gas Account?
  5. Why Does Internet Matter So Much on Opening Day?
  6. How Do You Take Over Premises From a Previous Operator?
  7. Get the Venue Connected Before Opening Week
  8. Frequently Asked Questions

Opening week is a bad time to discover the oven needs more power, the gas account was never opened or the EFTPOS terminals have no internet. Planning utilities for a new cafe should start when the lease is signed, not when the fit-out is nearly finished.

Hospitality premises have three connections that directly affect whether the doors can open: electricity, gas where the kitchen uses it, and internet for payments, bookings and ordering. Each follows a different network and lead time.

This guide explains the order to book them, what to check before signing and how to take over an existing venue without inheriting the previous operator’s accounts.

Market Overview: Key Insights 2026

  • Cafés, restaurants and takeaway food services supported 211,700 jobs in the June quarter 2026, up 1,300 from the previous quarter.
  • For a new restaurant, the AER says previous site usage may be used to estimate the new business’s annual energy consumption.
  • For internet, nbn recommends starting a business relocation 2–3 months ahead where possible.
  • A first nbn fixed-line service in a new development can involve an end-user contribution of up to $300 including GST.
  • In Victoria, the small-business electricity threshold is 40 MWh a year.

What Utilities Does a Café or Restaurant Need Before Opening?

A café or restaurant needs electricity that suits its equipment, gas if the kitchen uses mains gas, and internet for payments and ordering. Water and trade-waste arrangements are handled separately through the landlord or water authority.

The core utility scope is simple:

  • Electricity: refrigeration, lighting, coffee machines, dishwashers, ventilation and cooking equipment.
  • Gas: only where the kitchen equipment and premises use mains gas.
  • Internet: EFTPOS, booking systems, delivery platforms, phones, cloud software and guest Wi-Fi where offered.

For utilities for a new cafe, connection services can arrange energy and internet accounts, but they do not certify a commercial kitchen, size electrical loads or approve gas installations. Those jobs belong to licensed trades and the relevant authorities.

Before opening accounts, use the checklist for setting up electricity at new business premises so the ABN, handover date and meter information are ready.

What Should You Book First?

Book internet first when the lease is signed, then arrange gas and electricity for the handover date. Check the electrical and gas supply before committing to equipment that the premises may not support.

The table below gives a practical sequence for an existing hospitality premises.

Order Service or check When to start Why
1 Internet As soon as the lease is signed; ideally 2–3 months ahead nbn recommends early business relocation planning, and installations can involve provider or technician work.
2 Supply check Before signing the lease or ordering major equipment A phase or capacity change can require an electrician, landlord approval and distributor work.
3 Gas At least 3–5 business days before handover where an existing supply is present Gas can require meter access or a site visit and is less flexible than a remote electricity reconnection.
4 Electricity At least 1–3 business days before handover for a straightforward existing connection Existing meters can be quick, but access, meter work or a new connection can add time.

A simple example: for a venue taking possession on Monday 16 November, a safer sequence is to order internet when the lease is signed, verify the electrical and gas supply before the fit-out is locked in, and have the energy accounts confirmed well before the handover weekend.

Melbourne venues should also check the local distributor and meter arrangement. The guide to connections in Victoria explains the local energy process before the move-in request is lodged.

When Should You Book Café and Restaurant Utilities?

The safest order is to start internet early, check the premises supply before the fit-out, then have gas and electricity ready for handover.

Service or check
Planning sequence
Recommended timing
1

Internet

Opening-day systems

2–3 months ahead
2

Supply check

Power and gas capacity

Before fit-out
3

Gas

Existing supply

3–5 business days
4

Electricity

Existing connection

1–3 business days

Start first

Internet has the longest planning window and can affect EFTPOS, bookings and online orders.

Before handover

Have the gas and electricity accounts arranged before the venue changes hands.

View the planning data
Service or check When to start
Internet As soon as the lease is signed; ideally 2–3 months ahead
Supply check Before signing the lease or ordering major equipment
Gas At least 3–5 business days before handover where an existing supply is present
Electricity At least 1–3 business days before handover for a straightforward existing connection

Internet planning source: nbn business relocation guidance. Energy timing shown is the planning guidance used in this article for an existing hospitality premises. 

Does a Commercial Kitchen Need Three-Phase Power?

Many commercial kitchens use three-phase equipment, but the answer depends on the combined load of the actual ovens, dishwashers, refrigeration, coffee machines and ventilation installed at the premises.

A café electricity setup should therefore start with the equipment schedule, not an assumption. A smaller café may operate on a lighter supply, while a full commercial kitchen can have much higher simultaneous demand.

Have a licensed electrician compare the equipment load with the existing supply before signing the lease or committing to the fit-out. No one should open a switchboard or attempt electrical work simply to identify the supply type.

Jemena’s current guidance explains that changing an existing electricity connection from one phase to three phase is treated as an alteration to the connection. That means the distributor may be involved in addition to the electrician and landlord.

Where three-phase is important to the operation, follow the dedicated guide to check for three-phase power before the lease is finalised.

What Is Different About a Commercial Gas Account?

A commercial gas account is opened in the business entity’s name, and the existing meter and supply must be suitable for the kitchen’s total gas load. A licensed gasfitter should assess the installation itself.

A restaurant gas connection can involve significantly more usage than a household account because multiple appliances may operate for long hours. Give the retailer the ABN, address, handover date and MIRN where available, then keep the account process separate from the technical gas assessment.

A gasfitter can confirm whether the meter, regulator and internal installation suit the appliances. Do not attempt to change, relight or modify commercial gas equipment without the correct licensed trade.

High annual use can also affect whether the venue is treated as a small or large energy customer. Review small vs large business energy customers if the previous operator’s bill shows high consumption or the new kitchen will operate at a different scale.

new-cafe-restaurant-utility-connections-cta-1

Why Does Internet Matter So Much on Opening Day?

Without internet, card payments, online orders, bookings, cloud POS systems and delivery-platform tablets can all be affected, so internet should be treated as an opening-day utility rather than an office extra.

The nbn’s current business relocation page recommends starting a move 2–3 months in advance and checking which nbn technology is available at the new premises. That is a better planning benchmark than assuming the previous operator’s service can simply be transferred.

Use the business broadband page to check options at the address, then keep a mobile or 4G/5G fallback ready for opening week if payments or ordering depend on being online.

If you are taking over an existing venue or relocating an established business, the guide to move business internet without downtime covers overlap, number porting and backup connections.

For a newly developed premises, nbn says an end-user contribution of up to $300 including GST may apply to the first nbn order. The current new developments guidance explains when that charge can arise and who may ultimately pay it.

How Do You Take Over Premises From a Previous Operator?

Open your own accounts from the handover date and photograph the electricity and gas meters that day. Do not rely on the previous operator’s energy or internet accounts remaining active after settlement or lease handover.

The cleanest handover separates the previous business’s usage from yours.

Check When Why
Photograph electricity and gas meters Handover day Creates evidence of where your usage starts.
Open accounts in your business name For the handover date Prevents reliance on the previous operator’s account staying open.
Confirm internet service and phone numbers Before handover Existing numbers may need to be ported rather than cancelled.
Ask for a recent energy bill Before signing Shows NMI/MIRN, tariff information and historic usage.
Confirm power phase and major equipment Before signing Reduces the risk of discovering a supply mismatch after the lease is signed.

The Australian Government recommends telling the retailer early when a business is moving and taking meter readings at the old and new premises. The Energy Made Easy moving guidance supports that clean changeover approach.

For taking over a cafe utilities setup, arrange your own accounts rather than trying to inherit the old operator’s contract. The business moving service can coordinate the move-in date across energy and internet while each provider completes its own service order.

Once the account details are ready, you can also compare and connect electricity for your business using the new venue’s expected usage instead of assuming the former operator’s plan is suitable.

Our Melbourne connections team is based at Level 2, 134 Flinders Street, Melbourne VIC 3000. You can read reviews of our Melbourne connections team on Google Maps. For current connection enquiries, call 1300 362 580.

Get the Venue Connected Before Opening Week

A hospitality opening depends on several systems working together. Confirm the electrical and gas supply before the fit-out is locked in, order internet early, and open the energy accounts for the exact handover date.

For utilities for a new cafe, the biggest risk is not the paperwork itself; it is discovering too late that the premises needs technical work or that the internet installation cannot meet the opening date.

To coordinate the services that can be arranged together, contact Move-in Connect.

Frequently Asked Questions

How Early Should a Café Book Utilities?

Start when the lease is signed. Internet should be checked first, while electricity and gas at an existing premises should be arranged well before the handover date rather than left until opening week.

Can I Take Over the Previous Owner’s Energy Account?

No. Open your own account from the handover date. Take meter photographs that day so the start of your own electricity and gas usage is recorded.

Do All Cafés Need Three-Phase Power?

No. The requirement depends on the equipment and total electrical load. Have a licensed electrician assess the premises before committing to high-load commercial equipment.

Who Arranges a Supply Upgrade?

A licensed electrician and the local distributor are normally involved, with landlord approval where required. The electricity retailer does not perform the electrical upgrade itself.

Can Gas and Electricity Start on the Same Day?

They can be requested for the same handover date, but each connection follows its own distributor process. Gas should be arranged earlier because site access or a technician visit may be required.

Sources and further reading

Where the facts in this business moving guide come from.

  1. ABS: Quarterly tourism labour statisticsCited in the text above.
  2. AER: Energy and your business fact sheetCited in the text above.
  3. nbn co: Relocating your businessCited in the text above.
  4. nbn co: New developments FAQsCited in the text above.
  5. Energy Victoria: Buying energy for your businessCited in the text above.
  6. Jemena: Connection alterations FAQsCited in the text above.
  7. Energy Made Easy: Moving house or businessCited in the text above.